ContactPost:
CIVIL AVIATION AUTHORITY OF MALAYSIA Tel: 6-03-8778 4106 Email: ais@caam.gov.my URL: aip.caam.gov.my |
AIP Supplement for Malaysia![]() | AIRAC AIP SUP 36/25 Effective Date: 07 AUG 2025 Publication Date: 26 JUN 2025 |
1.1 This AIRAC AIP SUPP serves as additional information to the AIC 01/2023 regarding the works for the construction of New Royal Malaysia Police Air Operations Force Base at Kuching International Airport, Sarawak.
1.2 The duration of overall construction is Forty-Eight (48) months from 15th December 2021 until 31st December 2025 EST, of which this new Royal Malaysia Police Air Operations Force Base will replace the old base.
1.3 The purpose of this AIRAC AIP SUP is to notify the aviation industry of the schedule and the extent of the work areas due to the construction activities within Kuching International Airport.
2.1 The scope of works prescribed for the above exercise are as follows (Appendix 1 – Overall Layout and Appendix 2 – Layout Scope of Works): -
a) | Soil investigation, earthwork and drainage works. |
b) | New Parking Apron on elevated platform to accommodate one (1) Code B aircraft stand with power-in/power out operations and one (1) helicopter stand. |
c) | New Exit Taxiway for Code B aircraft operations with 10.5 m wide on ground and elevated platform to connect the new parking apron to the existing runway. |
d) | New Aeronautical Ground Lighting (AGL) installation and High Mast. |
e) | New Hangar. |
f) | New Administration Building. |
g) | New Storm Shelter. |
h) | New Engine Ground Run and Wash Bay. |
i) | New Multi Purpose Hall. |
j) | New Guard House. |
k) | New Road and Car Park facilities. |
l) | Airside and Landside Drainage. |
m) | Other Ancillary Buildings. |
3.1 The works programme is divided into two (2) main phases. (Appendix 3 – Layout of Works for Phase 1 and Phase 2)
Landside Area: Phase 1 & Phase 2 (Zone A)
Involves piling, excavation, structural and pavement works for construction partial of new exit taxiway, new elevated parking apron, hangarage facilities and other supporting buildings facilities.
Airside Area: Phase 2 (Zone B and Zone C)
Involves piling, excavation, structural and pavement works for construction of new exit taxiway, airside drainage, perimeter road, Aeronautical Ground Lighting and other associated works.
The tentative works are scheduled as follows:
PHASES | SCHEDULE | |
---|---|---|
1. | Phase 1 | FM 20211215 TIL 20251231 EST |
2. | Phase 2 | |
i) Zone A | FM 20231215 TIL 20251231 EST | |
ii) Zone B | FM 20240126 TIL 20251231 EST | |
iii) Zone C | FM 20240226 TIL 20251231 EST |
Construction works for Phase 1 and Phase 2 – Zone A (i.e. outside runway strip) will be carried out during normal airport operational hours or up to twenty-four (24) hours.
Construction works for Phase 2 - Zone B and Zone C (i.e. within runway strip and infringe the OLS) will be carried out during runway closure schedule from 1700 – 2100 UTC Daily.
4.1 Pilots are advised to take note of the precautions on the presence of open excavation, workers, construction materials and construction equipment, particularly while works within the areas are in progress.
Name (or designated) : Duty Executive, MASB Kuching
Tel: +6012-8520176
Email: masb_kch@malaysiaairports.com.my
Name (or designated) : Mr. Feroz (Project Manager), S&I Urban Designers Sdn Bhd
Tel: +6016-7540729
Email: mferoz.pgu@gmail.com (Project Manager)
Email: projekpgu@gmail.com (General email)
6.1 This AIRAC AIP Supplement supersedes NOTAM D0671/25 and will remain in force until the works are complete on 31st December 2025 EST. Any updates, changes and cancellation of this AIRAC AIP Supplement will be notified through NOTAM.
6 - END -